A Welcome Building update...

Posted: November 13, 2013 at 19:20 pm

Sophie Nash is Project Manager for The Westonbirt Project. She organises the logistics of the project, working with architects and project managers for various elements to deliver the works.

Now that the majority of the scaffolding is up, the carpenters have arrived and have started work on the roof.

Welcome Building

Below: timber purlins are the first element of the roof to be fixed into position.

Welcome Building

Below: timber sheeting is then fixed to the purlins. A roof membrane, timber battens and finally the Western red cedar shingles will then be laid and fixed onto the timber sheeting.

Welcome Building
A Welcome Building update...